PM 587 Week 4 Planning Risk Responses Example

Reviewed by Davina Cresswell, MBA · University of Phoenix · Updated

This PM 587 Week 4 example plans responses to a project's leading threats and opportunities, choosing a strategy for each, costing it, naming its owner and trigger and checking what risk remains afterward. University of Phoenix PM 587 asks for risk response planning in Week 4, and PM/587 rewards MBA students who justify each response by its cost against the exposure it removes. The case is the same Wichita launch, now that Week 3 has put numbers on its main drivers. The paper sets out the response strategies, plans responses for six threats and two opportunities, compares response costs with expected values, records residual and secondary risks, writes contingency plans with triggers and shows how contingency reserve is allocated.

CoursePM 587 Project Risk Management and Quality Assurance (PM/587)
Week4
Paper typeGraduate risk response plan
Lengthabout 1,208 words, 4 double-spaced pages plus title page and references
FormatAPA 7 student paper
SchoolUniversity of Phoenix
ProgramMBA
UpdatedOctober 2026

Free sample paper for PM 587 Week 4

1

Freezer Stock, a Rented Autoclave and an Executive Phone Call: Planning Risk Responses for a Composite Panel Launch

[Student Name]

University of Phoenix

PM/587: Project Risk Management and Quality Assurance

Week 4 Assignment

[Instructor Name]

[Date]

Plainsview Aerostructures, its responses, costs and owners are composites written for a model paper.

What this part is doingThe title names three different kinds of response, signaling that not every risk gets the same treatment.
2

The Week 3 simulation showed that Plainsview Aerostructures' first delivery of carbon-fiber panels for the new business jet had about a 22 percent chance of meeting month 14 and that customer drawings, autoclave access and prepreg supply drove most of the uncertainty. This paper plans responses for those and the other top risks, sized against what they could cost.

Choosing Strategies

The current standard describes response strategies for threats, avoid, escalate, transfer, mitigate and accept, and parallel strategies for opportunities, exploit, escalate, share, enhance and accept (Project Management Institute [PMI], 2021). Hillson (2002) argued that the risk process should treat opportunities with the same discipline as threats and proposed matching opportunity strategies to the familiar threat strategies, so that upside uncertainty is actively managed rather than left to chance. Zhang and Fan (2014) proposed an optimization approach to selecting risk responses that weighs each response's cost against the reduction in risk it achieves and the budget available, formalizing what project teams usually do by judgment. Plainsview's team applied the same logic informally: each response was compared with the expected cost of the risk it addresses.

What this part is doingThe cost-versus-exposure logic set out here is applied to every response below.
3

Threat 1: Single-Source Prepreg Supply

Strategy: mitigate now, with a longer-term change. Actions: build and hold eight weeks of frozen prepreg safety stock from month 3, stored at the supplier-specified temperature, at a cost of about $210,000 in material carrying cost and freezer space; negotiate an allocation clause guaranteeing Plainsview's launch volumes, with the supplier's sales director; begin qualifying a second source for the smaller panels after first delivery. Owner: purchasing manager. Trigger: any allocation notice. Residual: probability falls from 30 to about 10 percent of a disruption that delays production, and the impact of one shrinks to about two weeks. Secondary risk: stock expiring before use if the schedule slips; the stock will be rotated first in, first out.

Threat 2: Late Customer Drawings

Strategy: escalate and share. The cause sits with the customer, so the response belongs at the level that can influence it. Actions: the general manager calls the customer's program director to propose a trade: Plainsview accepts a design freeze on panel interfaces in exchange for early release of the four largest late drawings, and its engineers join the customer's design reviews for those parts. Owner: program manager, with the general manager. Trigger: drawings not released by month 3. Residual: probability falls from about 4 on the scale to 2 for the four largest parts; the two smaller late parts remain at risk but use short-lead aluminum tools.

Threat 3: Autoclave Conflict

Strategy: mitigate, with a contingency plan. Actions: a written slot agreement with the military program's manager, approved by the operations director, reserving twelve cure cycles for qualification in months 5 to 9. Contingency plan: rent cure time at an outside autoclave 180 miles away if two reserved slots are lost in a month, with a standing quote and logistics plan prepared now. Owner: autoclave supervisor. Trigger: loss of a reserved slot. Cost: about $15,000 to prepare the plan; about $90,000 if used.

A contingency plan written in a calm week is cheaper than one improvised after the trigger has fired.

Threat 4: Invar Tool Delivery

Strategy: transfer part of the impact and mitigate. Actions: a late delivery penalty in the tool contract and a weekly progress call with the tool builder; release the tool order for the two largest tools at 80 percent design maturity to gain four weeks, accepting modest rework risk. Owner: tooling engineer. Trigger: builder misses an interim milestone.

Threat 5: Prepreg Out-Time

Strategy: mitigate. Actions: cut ply kits in the order of layup, track out-time on each kit with a barcode and timer and schedule long layups only when an autoclave slot is confirmed. Owner: production supervisor. Cost: about $25,000 for the tracking system.

Threat 6: Technician Hiring Shortfall

Strategy: mitigate. Actions: a partnership with a local technical college's composites program for twelve trainees, starting in month 4, with a hiring bonus for graduates. Owner: human resources manager. Cost: about $120,000. Trigger: fewer than six hires by month 6.

Opportunities

Automated ply cutting: exploit. The machine is installed; programming it for all 22 parts by month 6 makes the opportunity certain and cuts layup time by about 15 percent. Owner: manufacturing engineer.

Out-of-autoclave material: enhance, then decide. Spend about $20,000 to obtain the customer's preliminary view, as Week 3 recommended, and commit the $380,000 qualification only if the view is favorable, raising the chance of approval before spending.

What this part is doingTreating opportunities with named owners and decisions follows the research cited above.
4

How Responses Were Tested With the People Who Must Carry Them Out

Before the plan went to the general manager, each owner walked through their response with the people who would do the work. The freezer stock plan went to the receiving supervisor, who pointed out that the existing freezer had room for only five weeks of stock; a rented freezer trailer, about $1,800 a month, was added. The ply-kit tracking plan went to two lead technicians, who asked that timers be visible from the layup table rather than only on a screen in the office. The autoclave contingency went to the shipping coordinator, who confirmed that cured parts could be moved back in an insulated truck within the material's handling limits. Small changes like these are where response plans usually fail if no one asks.

Communicating the Plan

The response plan was summarized on two pages for the general manager and the customer's supplier quality representative, showing the top risks, each response, its owner and the effect on the P80 dates. The customer received a version without cost details, which helped the drawing negotiation: it showed that Plainsview was taking its own risks seriously while asking the customer to act on one.

Accepted Risks

Lower-ranked risks, such as the inspection report format, are accepted with contingency plans and triggers rather than active responses, since their expected costs are below the cost of mitigation.

Response Cost Against Exposure

Responses for the six threats cost about $395,000 to implement, plus about $90,000 if the autoclave contingency is triggered. Re-running the Week 3 model with the responses in place moved the P80 delivery date from mid-month 16 to early month 15 and the P80 cost from about $7.1 million to about $6.7 million. The exposure removed, about $400,000 at P80 cost plus five to six weeks of schedule, justifies the spending.

Reserve Allocation

Contingency reserve is set at about $500,000, sized to the residual exposure at P80 after responses, and allocated to specific risks: about $90,000 for the autoclave contingency, about $150,000 for residual tool delays and expediting, about $160,000 for yield shortfall and scrap and about $100,000 for residual supply and staffing effects. A management reserve of $250,000, held by the general manager, covers unidentified risks.

Conclusion

Plainsview's response plan matches strategies to risks: mitigation for supply, out-time and staffing, escalation for the customer's drawings, mitigation with a prepared contingency for autoclave capacity, partial transfer for tooling and active pursuit of two opportunities. Each response has an owner, a trigger and a cost, residual and secondary risks are recorded, and reserves follow the exposure that remains. The responses move the likely delivery date earlier and justify their cost.

5

References

Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, 20(3), 235-240. https://doi.org/10.1016/S0263-7863(01)00074-6

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.

Zhang, Y., & Fan, Z.-P. (2014). An optimization method for selecting project risk response strategies. International Journal of Project Management, 32(3), 412-422. https://doi.org/10.1016/j.ijproman.2013.06.006

What the PM 587 Week 4 instructions ask

Week 4 assignments in PM 587 typically ask graduate students to develop risk responses for the project's most significant risks. Prompts may call for selecting strategies for threats, such as avoid, transfer, mitigate, accept or escalate, and for opportunities, such as exploit, enhance, share or accept, naming owners and actions, setting triggers and contingency plans, estimating response costs, identifying residual and secondary risks and explaining how reserves will be used. Base the responses on the analysis from earlier weeks, show why each strategy fits the risk and back the choices with journal studies of response selection and opportunity management, cited in APA.

How this PM 587 Week 4 example is built

The model plan addresses the risks that the Week 3 simulation showed driving the schedule. For the single-source prepreg, it combines mitigation, eight weeks of frozen safety stock and an allocation clause in the supply contract, with a longer-term second-source qualification. Late customer drawings are escalated to the customer's program director with an offer to trade a design freeze for early release. Autoclave conflict is mitigated by a written slot agreement with the military program and backed by a contingency plan to rent outside autoclave time. Each response has a cost, an owner, a trigger and a residual rating. Two opportunities, automated ply cutting and the alternative material, are exploited and enhanced. A reserve table ties contingency to the residual exposure.

PM 587 Week 4 grading rubric: where the points go

Strong response plans are specific, proportionate and complete. Graders look for a strategy matched to each risk with reasons, concrete actions with owners and dates, triggers and contingency plans for risks that are accepted or may still occur, and response costs compared with the exposure they remove. Credit goes to identifying residual and secondary risks, to including opportunities with positive strategies and to linking contingency reserve to the residual exposure rather than a flat percentage. Research on response selection and opportunity management supports the plan. A response table that a team could act on, logical flow and properly cited APA sources complete the top papers.

PM 587 Week 4 help: mistakes to avoid

Responses written as intentions, such as monitor closely, are the most common weakness; a response needs an action, an owner and a date. Another frequent problem is choosing mitigation for everything. Some risks are better transferred, escalated or accepted with a contingency plan. Students also forget that responses cost money and can create new risks, such as safety stock that expires in the freezer. Name secondary risks. Opportunities are often left out or given a single line; plan them with the same care. Finally, connect reserves to what remains after responses, not to the original exposure. If your responses read like a wish list, a tutor can help you turn them into actions.

Related PM 587 sample papers

Other PM 587 week samples

More MBA sample papers

PM 587 Week 4 questions, answered

What does PM 587 Week 4 usually cover?

It usually covers planning risk responses: choosing strategies for threats and opportunities, naming owners, setting triggers and contingency plans, costing responses, identifying residual and secondary risks and allocating reserves.

Where can I find a free PM 587 Week 4 sample paper?

The Week 4 paper above plans responses to six threats and two opportunities in an aircraft panel launch and is free to read in full.

What are the risk response strategies for threats?

Avoid, which removes the cause; transfer, which shifts the impact to another party; mitigate, which reduces probability or impact; accept, which plans to absorb it; and escalate, which hands it to a higher level that owns it.

What is a secondary risk?

A new risk created by carrying out a risk response, such as stored material expiring because safety stock was built up to guard against a supply cut.

What is a contingency plan in risk management?

A plan prepared in advance and put into action only if a trigger shows that a risk is occurring, such as renting outside equipment if internal capacity becomes unavailable.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official University of Phoenix document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.