| Course | PM 340 Project Delivery and Measurement (PM/340) |
|---|---|
| Week | 4 |
| Paper type | Earned value analysis |
| Length | about 1,172 words, 4 double-spaced pages plus title page and references |
| Format | APA 7 student paper |
| School | University of Phoenix |
| Program | BS in Business |
| Updated | October 2026 |
Free sample paper for PM 340 Week 4
Week 40 of 62: An Earned Value Analysis and Sponsor Dashboard for a Museum Gallery Running Late
[Student Name]
University of Phoenix
PM/340: Project Delivery and Measurement
Week 4 Assignment
[Instructor Name]
[Date]
Prairie River Museum of Natural History, its earned value data and forecasts are composites written for a model paper.
The Prairie River Museum of Natural History, an invented museum in Omaha, Nebraska, is fitting out its new mammoth and ground sloth gallery on a 62-week schedule ending at a fixed opening before spring break. Week 3 set the baselines and measures. This paper applies earned value management at the end of week 40, when the project manager, Teresa Whitfield, suspected that fabrication delays were pushing the project behind and that cost was creeping upward. It calculates performance, forecasts the outcome, recommends recovery actions and presents a dashboard for the sponsor.
The Three Basic Values
Earned value management compares three amounts at a status date (Project Management Institute [PMI], 2021). Planned value is how much of the budget the schedule says should have been put to work by that date. Earned value is the budget belonging to the pieces that are in fact finished. The third figure, actual cost, records what the museum has paid to get those pieces done. Anbari (2003) described how these three values, set against a time-phased baseline, allow a project's cost and schedule performance to be measured on one scale and forecasts to be made from current trends.
The gallery's budget at completion for measured work is $3,120,000, the $3.42 million cost baseline minus $300,000 of contingency, which is tracked separately. Each work package, such as a case, earns its budget when it passes shop inspection and again when installed, using a 50/50 rule for fabrication and installation. At the end of week 40:
Planned value (PV): $2,050,000.
Earned value (EV): $1,880,000.
Actual cost (AC): $2,010,000.
Variances and Indexes
Schedule variance is EV minus PV: $1,880,000 minus $2,050,000 equals negative $170,000. The project has completed $170,000 less work than planned.
Cost variance is EV minus AC: $1,880,000 minus $2,010,000 equals negative $130,000. The work completed cost $130,000 more than its budget.
The schedule performance index is EV divided by PV: 1,880,000 / 2,050,000 = 0.92. The project is accomplishing about 92 cents of planned work for every dollar of work scheduled.
The cost performance index is EV divided by AC: 1,880,000 / 2,010,000 = 0.94. Each dollar spent is producing about 94 cents of budgeted work.
Both indexes are below 1.0. The cost problem is modest; the schedule problem is more serious given a fixed opening.
Forecasting the Final Cost
Three estimates at completion (EAC) reflect different assumptions:
If current cost performance continues: EAC = BAC / CPI = 3,120,000 / 0.935 = about $3,336,000.
If remaining work proceeds at budget: EAC = AC + (BAC minus EV) = 2,010,000 + 1,240,000 = $3,250,000.
If both cost and schedule performance affect the rest of the work: EAC = AC + (BAC minus EV) / (CPI × SPI) = 2,010,000 + 1,240,000 / (0.935 × 0.917) = 2,010,000 + about 1,446,000 = about $3,456,000.
The first forecast, about $3,336,000, implies a variance at completion of about negative $216,000 and an estimate to complete of about $1,326,000. It fits within the $300,000 contingency. The third, about $3,456,000, would exceed it by about $36,000 and would require the director to release management reserve. The second is optimistic, because nothing in the data suggests cost performance will suddenly improve.
Dividing the budget left for unfinished work by the money left in the budget gives the to-complete index: 1,240,000 / 1,110,000 = 1.12. It shows that finishing within the $3.12 million budget for measured work would require the remaining work to be done 12 percent more efficiently than planned. Since the project has performed at 0.94, that is unlikely. Contingency, not efficiency, will have to cover the overrun.
A to-complete index well above the index achieved so far is a forecast telling the sponsor to stop hoping.
Forecasting the Finish With Earned Schedule
Dollar-based schedule variance has a known flaw: at completion, EV equals PV, so SPI returns to 1.0 even for a late project. Earned schedule measures time instead. In the baseline, planned value reached $1,860,000 at the end of week 37 and $1,920,000 at the end of week 38. The current EV of $1,880,000 falls one-third of the way between, so earned schedule is about 37.3 weeks. The time-based index is 37.3 / 40 = 0.93, and the project is about 2.7 weeks behind. At that rate, the 62-week schedule would take 62 / 0.93, or about 66.4 weeks, finishing roughly four weeks after the opening date.
Vanhoucke and Vandevoorde (2007) tested duration forecasting methods on simulated project networks and reported that forecasts built on earned schedule were, on the whole, more dependable than the methods based on dollar indexes, particularly in the later stages of projects. Lipke et al. (2009) analyzed performance index data from real projects and argued that statistical analysis of earned schedule indexes can give managers early warning of likely outcomes. The museum is in its final third, so the earned schedule forecast deserves more weight than the dollar SPI.
What Is Driving the Results
The variances trace to the fabricator. Eleven cases were scheduled to pass shop inspection by week 40, but only seven have, after a supplier of low-reflection glass shipped late. Overtime at the fabricator to recover part of the delay raised costs, and two cases needed rework after inspection.
Recovery Actions
Whitfield recommends three actions. First, add a second installation crew from the fabricator for weeks 46 to 58, at about $48,000, so that installation can run in parallel on both sides of the gallery. Second, move the media installation, which does not depend on the late cases, two weeks earlier. Third, install the four delayed cases last and accept that the members' soft opening will take place with them covered if necessary. With these changes, the earned schedule forecast falls to about 62.5 weeks, close enough to recover within the remaining float in the final week. The added crew raises the likely EAC to about $3,384,000, still within contingency.
The Sponsor Dashboard
The deputy director receives a one-page dashboard every two weeks. It shows six numbers: SPI, CPI, earned schedule weeks behind, EAC against the $3.42 million baseline, remaining contingency and requirements accepted, each colored green, amber or red against thresholds agreed in Week 3. A three-sentence narrative explains the main problem, the action being taken and any decision needed. This week the dashboard shows SPI and earned schedule in red, CPI and EAC in amber and requirements in green, and asks the sponsor to approve the second crew.
Conclusion
Earned value analysis at week 40 confirms what the project manager suspected and puts numbers on it: the gallery is about 2.7 weeks behind and about 7 percent over cost for the work completed. Forecasts suggest the overrun can be absorbed by contingency, but the schedule cannot recover without action. A second crew, earlier media work and a revised installation sequence give the museum a realistic path to its opening date, and a six-number dashboard gives the sponsor what is needed to approve it.
References
Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23. https://doi.org/10.1177/875697280303400403
Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27(4), 400-407. https://doi.org/10.1016/j.ijproman.2008.02.009
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.
Vanhoucke, M., & Vandevoorde, S. (2007). A simulation and evaluation of earned value metrics to forecast the project duration. Journal of the Operational Research Society, 58(10), 1361-1374. https://doi.org/10.1057/palgrave.jors.2602296
What the PM 340 Week 4 instructions ask
Week 4 assignments in PM 340 usually ask students to apply earned value management to project data and to present performance in a dashboard or report. Common requirements are calculating planned value, earned value and actual cost, schedule and cost variances, the schedule and cost performance indexes, estimates at completion and to complete, variance at completion and sometimes the to-complete performance index. Many prompts also ask students to interpret the results, recommend actions and design or describe a dashboard for stakeholders. Use the data given or build a realistic example, show every formula and calculation, explain what each result means and cite the standard and research on earned value in APA format.
How this PM 340 Week 4 example is built
The sample paper is built around one status date. It explains planned value, earned value and actual cost in terms of the gallery's work packages and then calculates the variances and indexes: the project has earned $1.88 million of work against $2.05 million planned and $2.01 million spent. Three forecasts show the range of likely final costs, and the to-complete index shows how hard the remaining work must perform to stay on budget. Because dollar-based schedule measures lose meaning late in a project, the paper adds an earned schedule calculation that predicts a finish about four weeks late. Recovery actions follow, and a final section describes the dashboard and why it shows only six numbers and three colors.
PM 340 Week 4 grading rubric: where the points go
Accuracy carries much of the weight on this paper, so every calculation must be correct and shown. Beyond accuracy, graders reward interpretation: what a cost index of 0.94 means for the budget, whether a forecast is realistic and what the sponsor should decide. Papers that compare forecasting methods and explain their assumptions show strong understanding. Recognizing the limits of earned value, such as how its schedule measures behave late in a project, earns extra credit. The dashboard should be designed for its audience, with few measures, clear thresholds and a short narrative. A clean layout of formulas and results, logical flow from numbers to actions and correct APA formatting complete a top paper.
PM 340 Week 4 help: mistakes to avoid
Arithmetic and sign errors cause many lost points. Remember that variances are earned value minus planned value or actual cost, so negative means behind or over. Students also mix up which value goes on top in an index; check that an index below 1.0 means poor performance. Another common gap is calculating everything and interpreting nothing. After each result, write a sentence about what it means. Many papers use a single estimate at completion without saying what it assumes; compare at least two. Some dashboards are cluttered with every number calculated. Choose what the sponsor needs. If your figures do not reconcile, a tutor can walk through each formula with your data.
Related PM 340 sample papers
Other PM 340 week samples
- PM 340 Week 1: The Project Work Domain
- PM 340 Week 2: Delivering Scope and Quality
- PM 340 Week 3: Measures and Baselines
- PM 340 Week 5: Managing Uncertainty
More BS in Business sample papers
- MKT 498 Week 4: Promotion, PR and Events
- PM 300 Week 4: Decision Making and Problem Solving
- PM 310 Week 4: The Planning Domain
- PM 350 Week 1: Organizational Project Management
PM 340 Week 4 questions, answered
What does PM 340 Week 4 usually cover?
It usually covers earned value management and dashboards: calculating planned value, earned value, actual cost, variances, performance indexes and forecasts and presenting project performance clearly to stakeholders.
Where can I find a free PM 340 Week 4 sample paper?
The earned value analysis above, worked step by step for a museum gallery at week 40 with forecasts and a sponsor dashboard, is a free Week 4 sample.
How do you calculate the cost performance index?
Take the earned value and split it by what has been spent. Anything under 1.0 says each dollar is buying less finished work than the budget assumed, and anything over 1.0 says the work is coming in cheaper than planned.
What is the difference between EAC and ETC?
The estimate at completion is the expected total cost of the project. The estimate to complete is the expected cost of the remaining work, so EAC equals actual cost plus ETC.
What is earned schedule?
An extension of earned value that measures schedule performance in units of time, by finding when the current earned value should have been earned according to the plan.
Write yours, or have the desk draft it
This paper is an original model document written by our desk, not a submitted student paper and not an official University of Phoenix document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.
Request this one custom, free · All PM 340 week samples · All courses