OPS 405 Week 5 ERP Implementation Example

Reviewed by Davina Cresswell, MBA · University of Phoenix · Updated

This OPS 405 Week 5 example plans the implementation of an enterprise resource planning system from vendor selection through go-live and stabilization. The closing week of University of Phoenix OPS 405 is about ERP implementation, and the course rewards BS in Business students who plan for people, data and testing as carefully as for software. Saginaw Valley, the invented cylinder plant whose processes, planning cycle, master schedule and MRP filled the earlier weeks of OPS/405, is the case. The paper chooses a phased approach over a single cutover, sets out the project organization, plans configuration with minimal customization, data migration and cleansing, three rounds of testing, training and cutover timed after the spring peak, describes hypercare support and lists the measures and risks the steering committee will watch.

CourseOPS 405 Enterprise Resource Management (OPS/405)
Week5
Paper typeERP implementation plan
Lengthabout 1,037 words, 4 double-spaced pages plus title page and references
FormatAPA 7 student paper
SchoolUniversity of Phoenix
ProgramBS in Business
UpdatedOctober 2026

Free sample paper for OPS 405 Week 5

1

Go-Live After Harvest Season: An ERP Implementation Plan for a Michigan Hydraulic Cylinder Maker

[Student Name]

University of Phoenix

OPS/405: Enterprise Resource Management

Week 5 Assignment

[Instructor Name]

[Date]

Saginaw Valley Fluid Power, its project, budget and dates are composites written for a model paper.

What this part is doingThe title ties go-live timing to the business calendar, a theme of the plan.
2

Over four weeks, this course traced Saginaw Valley Fluid Power's processes, designed its sales and operations planning, built a master schedule and worked through material and capacity planning. The composite Saginaw, Michigan, cylinder maker has selected an ERP system from a vendor serving mid-size discrete manufacturers, with a budget of about $1.6 million over 18 months for licenses, implementation services, data work, training and internal staff time. This paper sets out the implementation plan.

Phased, Not Big Bang

A big-bang cutover switches every function at once: faster and without temporary interfaces, but with all risk concentrated on one weekend. A phased approach spreads risk but runs longer and needs temporary links to old systems. Markus et al. (2000) studied companies that had adopted ERP and found that problems were common in every phase, from configuration through shakedown and onward, and that many companies experienced business disruption after going live. For a plant whose customers' assembly lines depend on its deliveries, disruption is costly. The committee chose three phases:

Phase 1, months 1 to 7: finance, purchasing and inventory, going live in month 7, after the spring peak.

Phase 2, months 6 to 13: planning, master scheduling, MRP and the shop floor, going live in month 13, in the autumn lull.

Phase 3, months 12 to 18: sales, available-to-promise, electronic data interchange with customers and a customer portal.

What this part is doingTiming each go-live to the business calendar is the plan's main risk control.
3

Project Organization

The executive sponsor is the president, who chairs a monthly steering committee. The project manager, the operations controller, works on the project full time. Each process has a business owner: the sales director for order-to-cash, the purchasing manager for procure-to-pay, the plant manager for plan-to-produce and the controller for record-to-report. Twelve super-users, one or two from each department, are released for 40 percent of their time to configure, test and train. The vendor provides a solution architect and functional consultants. Holland and Light (1999) proposed a model of critical success factors for ERP implementation that separates strategic factors, such as a clear vision, top management support and project schedules and plans, from tactical factors, such as client consultation, personnel, configuration, testing and monitoring. The organization above addresses both levels.

Configuration and Customization

The team will adopt the system's standard processes wherever possible. A customization will be approved only if a gap affects customers or regulatory compliance and the steering committee agrees. Two gaps qualify: the electronic data interchange formats required by two large equipment builders and the test-certificate printout customers require with each cylinder. Engineering's request to replicate its drawing database inside the ERP was declined; the systems will be linked instead.

Every customization is a promise to rebuild it at every upgrade.

Data Migration

Data work starts in month 1 because it is the longest task. Item records, about 4,800, will be reviewed by owners named in Week 1; obsolete items, about 900, will not migrate. Bills of materials for 1,900 models will be validated by building ten sample cylinders on paper against each bill. Routings and standard times will be checked against shop records. Open orders, inventory balances and supplier and customer records migrate at each phase's cutover weekend, with reconciliations signed by the process owner.

Testing

Testing builds in three rounds. Unit tests check each configured function. Two conference room pilots run realistic scenarios end to end, such as a tractor builder's release loaded through electronic data interchange, confirmed with available-to-promise, planned through MRP, built, tested, shipped and invoiced. A final integration test runs a full simulated week of transactions with super-users at their desks. Any defect rated critical must be fixed and retested before go-live.

Training

Training is by role, not by module. Robey et al. (2002) studied enterprise system implementations and found that firms had to overcome knowledge barriers, both learning the system's configuration and learning new ways of working, and that how they addressed these barriers shaped outcomes. Super-users train their colleagues in short sessions using the company's own data, followed by practice in a training environment. Shop floor workers learn to report labor and material on terminals in one-hour sessions at their work centers.

What this part is doingTraining by role reflects research on the knowledge barriers that implementations face.
4

Cutover and Hypercare

Each go-live happens over a weekend, with a checklist of about 150 steps, a final data load, reconciliation and a decision point on Sunday afternoon: proceed or roll back to the old system. For four weeks after go-live, hypercare provides vendor consultants on site, super-users on every shift and a daily issue meeting.

Change Management Beyond Training

Training teaches people which screens to use; change management helps them accept why the work is changing. Customer service staff, for example, lose the freedom to promise dates from experience and must quote from available-to-promise. The sales director will explain the reason at a team meeting, show how quoted dates compared with actual deliveries last year and invite the staff to watch the measure improve. Shop leads who helped write test scenarios will introduce the terminals to their crews. A short pulse survey after each go-live asks users whether they feel ready, and low scores trigger extra coaching.

Budget Breakdown

Of the $1.6 million budget, about $420,000 covers subscription and license fees for the first two years, about $560,000 the vendor's implementation services, about $180,000 data cleansing and migration support, about $90,000 training materials and sessions, about $250,000 backfill for super-users and the project manager and about $100,000 contingency.

Measures and Risks

The steering committee tracks schedule, budget and open critical issues during the project, and after each go-live: order confirmation time, on-time delivery, inventory accuracy, invoice errors and the number of manual workarounds. Main risks are key users pulled back into daily work, data cleansing running late and resistance on the shop floor; responses include protected time for super-users, early data work and involving shop leads in testing.

Conclusion

Saginaw Valley's ERP implementation is phased around its seasonal business, owned by process leaders rather than the IT function, configured with minimal customization, supported by early data cleansing, three rounds of testing and role-based training and protected by cutover checklists, a rollback option and hypercare. The measures that defined the case for integration in Week 1 will show whether the implementation delivered it.

5

References

Holland, C. P., & Light, B. (1999). A critical success factors model for ERP implementation. IEEE Software, 16(3), 30-36. https://doi.org/10.1109/52.765784

Markus, M. L., Axline, S., Petrie, D., & Tanis, C. (2000). Learning from adopters' experiences with ERP: Problems encountered and success achieved. Journal of Information Technology, 15(4), 245-265. https://doi.org/10.1080/02683960010008944

Robey, D., Ross, J. W., & Boudreau, M.-C. (2002). Learning to implement enterprise systems: An exploratory study of the dialectics of change. Journal of Management Information Systems, 19(1), 17-46. https://doi.org/10.1080/07421222.2002.11045713

What the OPS 405 Week 5 instructions ask

The last OPS 405 assignment usually asks students to plan or evaluate an ERP implementation. Prompts may cover the choice between big-bang and phased approaches, project organization and roles, configuration versus customization, data migration, testing, training, cutover planning, change management, post-implementation support and critical success factors and risks. Some versions ask students to tie the plan to processes developed earlier in the course. Base the plan on the organization from earlier weeks, give a realistic timeline and budget and support the approach with information systems research on ERP implementation cited in APA. Explain how the company will know the implementation succeeded and what it will do if a go-live goes badly.

How this OPS 405 Week 5 example is built

This model begins with the decision the steering committee faced: switch every function on one weekend or in phases. It chooses phases: finance and purchasing first, then planning and the shop floor, then sales and customer portals, each going live after the spring order peak. Roles are set for an executive sponsor, a project manager, process owners from each department, super-users and the vendor's consultants. Configuration follows standard processes unless a gap affects customers, and the paper explains why customization is limited. Data migration covers cleaning 4,800 item records and 1,900 bills of materials. Testing runs through unit tests, conference room pilots and a full integration test. Training, cutover, hypercare and measures complete the plan.

OPS 405 Week 5 grading rubric: where the points go

High marks on an implementation plan require realism and attention to the organization. Graders look for a reasoned choice of approach, clear roles with business ownership, a sensible stance on customization, a data migration plan, testing that progresses from components to end-to-end scenarios and training targeted by role. Credit goes to a cutover plan with a rollback option, post-go-live support and measures of success, along with honest risks. Research on ERP implementation should inform the plan. A realistic timeline and budget, logical organization and APA references in correct form complete a strong submission, and a short note on what the company would do if a go-live failed shows mature planning.

OPS 405 Week 5 help: mistakes to avoid

Implementation plans often read like software installation guides. Put people first: who owns each process, who decides on changes and how users will learn. Another frequent problem is heavy customization justified by current habits; every customization raises cost and makes upgrades harder. Explain when it is worth it. Students also underplan data migration, which consumes more time than expected; budget for cleansing. Testing sections sometimes list test types without scenarios; describe end-to-end tests such as an order from entry to invoice. Cutover plans often lack a fallback; include one. Finally, define how success will be measured after go-live. If your timeline feels unrealistic, a tutor can help you check it against the scope.

Related OPS 405 sample papers

Other OPS 405 week samples

More BS in Business sample papers

OPS 405 Week 5 questions, answered

What does OPS 405 Week 5 usually cover?

It usually covers ERP implementation: approach, project organization, configuration and customization, data migration, testing, training, cutover, post-implementation support, success factors and risks.

Where can I find a free OPS 405 Week 5 sample paper?

The Week 5 paper above plans a phased ERP implementation for a hydraulic cylinder maker and is free to read in full.

What is the difference between a big-bang and a phased ERP implementation?

A big-bang approach switches all modules and sites at once. A phased approach implements modules or sites in stages, reducing risk at the cost of a longer project and temporary interfaces.

What is a conference room pilot?

A testing exercise in which users run realistic business scenarios through the configured system in a controlled setting before go-live.

What is hypercare after ERP go-live?

A period of intensive support after go-live, with extra staff and fast issue resolution, while users adjust and early problems are fixed.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official University of Phoenix document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.