OPS 405 Week 4 Material and Capacity Planning Example

Reviewed by Davina Cresswell, MBA · University of Phoenix · Updated

This OPS 405 Week 4 example works through material requirements planning and capacity requirements planning, the two calculations that turn a master schedule into purchase orders, work orders and machine loads. University of Phoenix OPS 405 covers material and capacity planning in Week 4, and OPS/405 expects BS in Business students to explode a bill of materials, net requirements against inventory, offset by lead time and then test the resulting work against capacity. The plant is the composite Michigan hydraulic cylinder maker whose master schedule was built in Week 3. The paper sets out the boom cylinder's bill of materials, works a full MRP record for a shared seal kit, summarizes planned orders for other components, loads the rod machining center week by week, resolves an overload and explains the settings that make MRP trustworthy.

CourseOPS 405 Enterprise Resource Management (OPS/405)
Week4
Paper typeMRP and capacity planning analysis
Lengthabout 1,053 words, 4 double-spaced pages plus title page and references
FormatAPA 7 student paper
SchoolUniversity of Phoenix
ProgramBS in Business
UpdatedOctober 2026

Free sample paper for OPS 405 Week 4

1

Exploding the Boom Cylinder: Material Requirements and Capacity Requirements Planning at a Hydraulic Cylinder Plant

[Student Name]

University of Phoenix

OPS/405: Enterprise Resource Management

Week 4 Assignment

[Instructor Name]

[Date]

Saginaw Valley Fluid Power, its bills of materials, lead times and loads are composites written for a model paper.

What this part is doingThe title's verb is the MRP term for breaking a product into its parts.
2

Week 3 built a master production schedule for Saginaw Valley Fluid Power, the composite cylinder plant in Saginaw, Michigan, including lots of 200 BC-4520 boom cylinders in weeks 2, 4 and 7. The master schedule says what to finish; it does not say what to buy, what to make in the machine shop or whether the machines can handle it. Material requirements planning (MRP) and capacity requirements planning (CRP) answer those questions.

What MRP Needs

MRP uses three inputs: the master schedule, the bill of materials for each end item and inventory records showing on-hand quantities, open orders, lead times and lot-sizing rules. Orlicky (1975), who popularized MRP, argued that components of an end item should be planned from the schedule of that end item rather than from their own past usage, because their demand is dependent. Vollmann et al. (2005) emphasized that MRP's output depends on accurate records and realistic parameters.

The Boom Cylinder's Bill of Materials

One BC-4520 cylinder requires: one barrel tube assembly, made in house from purchased honed tubing and two welded ports; one chrome-plated rod, machined in house from purchased chrome bar; one piston and one gland, machined in house from bar stock; one seal kit, purchased; and two clevises, purchased as forgings and machined. Assembly and testing follow. Purchased lead times are three weeks for seal kits and five weeks for chrome bar; machining takes one week.

What this part is doingListing make and buy items separately shows which planned orders become work orders and which become purchase orders.
3

An MRP Record for the Seal Kit

The SK-45 seal kit is used by the BC-4520 and by another model scheduled for 150 units in weeks 3 and 6. Gross requirements by week: week 1, 0; week 2, 200; week 3, 150; week 4, 200; week 5, 0; week 6, 150; week 7, 200; week 8, 0. On hand at the start: 260. A scheduled receipt of 300 arrives in week 1. Lot size: multiples of 250, the supplier's pack quantity. Lead time: three weeks.

Projected on hand: week 1, 260 plus 300 = 560. Week 2, 560 minus 200 = 360. Week 3, 360 minus 150 = 210. Week 4, 210 minus 200 = 10. Week 5, 10. Week 6, 10 minus 150 would leave minus 140, a net requirement of 140, covered by a planned receipt of 250, leaving 110. Week 7, 110 minus 200 would leave minus 90, a net requirement of 90, covered by another planned receipt of 250, leaving 160. Week 8, 160.

Planned order releases, offset three weeks: 250 in week 3, for receipt in week 6; 250 in week 4, for receipt in week 7. When week 3 arrives, the buyer converts the first planned order into a purchase order.

A seal kit ordered too late stops a cylinder that every other part is ready for.

Other Components in Summary

Chrome bar, with a five-week lead time, must be released almost immediately for the week 7 lot and one week ago for the week 4 lot; MRP flags the late order as an exception, and the buyer expedites it from the supplier's local warehouse. Pistons and glands generate machining work orders released one week before each assembly lot. Clevis forgings are covered by inventory until week 6.

Capacity Requirements Planning

MRP assumes unlimited capacity, so CRP checks it. The rod machining center, a CNC lathe that turns and threads chrome rods and machines pistons and glands, has about 120 available hours a week. Converting released and planned work orders for all models into hours by week gives: week 1, 104 hours; week 2, 112; week 3, 138; week 4, 96; week 5, 118; week 6, 109. Week 3 is overloaded by 18 hours because rod orders for two large lots coincide.

Resolving the Overload

The planner considered four options. Overtime on Saturday, about 10 hours, costs about $1,100 in premium. Moving one rod order of about 9 hours into week 2, which has 8 spare hours, is possible because the bar is already in stock. An older manual lathe can turn simpler rods at about half the speed. Delaying a lot would break the master schedule's frozen zone. The planner moved one order into week 2, sent about 5 hours of simple rods to the manual lathe and scheduled 5 hours of Saturday overtime. Enns (2001) studied MRP systems and found that lot sizes and planned lead time settings significantly affect performance, including the tendency of loads to bunch; the plant will review whether smaller rod lots would smooth the lathe's load.

What this part is doingWeighing options with their costs turns the capacity check into a decision.
4

How Planners Use the Output

MRP produces hundreds of planned orders and exception messages each week, more than planners can review one by one. Saginaw Valley's planners work by exception: each morning they review messages telling them to release an order, expedite a late one, push one out because demand moved or cancel one that is no longer needed. They act on messages inside the next three weeks first, since those affect the frozen schedule, and batch the rest for a Friday review. Over time the number of expedite messages is itself a measure of how well the plan is working; a rising count signals bad lead times or unstable schedules.

Making MRP Trustworthy

MRP is only as reliable as its inputs. Saginaw Valley will count seal kits and chrome bar monthly and other items quarterly, target 97 percent inventory accuracy, review supplier lead times quarterly against actual deliveries and require engineering changes to bills of materials to be released before the affected lots enter the frozen zone. Hopp and Spearman (2004) argued that what distinguishes pull systems is a cap on work in process, and that MRP-based push systems can perform well when combined with such limits and realistic lead times. The plant will also cap work released to the lathe at two weeks of load.

Conclusion

MRP translates Saginaw Valley's master schedule into a time-phased plan for every component: for the SK-45 seal kit, two planned releases of 250 in weeks 3 and 4; for chrome bar, an expedited order flagged as late. CRP then shows that those plans overload the rod lathe in week 3, resolved by moving work earlier, using an alternate machine and a few hours of overtime. Accurate inventory, realistic lead times and controlled changes keep both calculations worth trusting.

5

References

Enns, S. T. (2001). MRP performance effects due to lot size and planned lead time settings. International Journal of Production Research, 39(3), 461-480. https://doi.org/10.1080/00207540010002810

Hopp, W. J., & Spearman, M. L. (2004). To pull or not to pull: What is the question? Manufacturing & Service Operations Management, 6(2), 133-148. https://doi.org/10.1287/msom.1030.0028

Orlicky, J. (1975). Material requirements planning: The new way of life in production and inventory management. McGraw-Hill.

Vollmann, T. E., Berry, W. L., Whybark, D. C., & Jacobs, F. R. (2005). Manufacturing planning and control for supply chain management (5th ed.). McGraw-Hill/Irwin.

What the OPS 405 Week 4 instructions ask

Week 4 assignments in OPS 405 usually ask students to explain and apply material requirements planning and capacity requirements planning. Prompts may ask for a bill of materials, the inputs MRP needs, a time-phased record showing gross requirements, scheduled receipts, projected on hand, net requirements, planned order receipts and releases, lot sizing and lead time offset and a capacity requirements plan that compares load with available capacity at a work center. Some versions ask how to resolve overloads and how parameter settings affect results. Show calculations period by period, explain each step and support the analysis with manufacturing planning and control sources cited in APA.

How this OPS 405 Week 4 example is built

Our worked example starts with the bill of materials for a boom cylinder: barrel tube, chrome rod, piston, gland, seal kit, two clevises and welded ports. MRP needs the master schedule, these bills and accurate inventory and lead-time records. A full eight-week record for the seal kit, used by the boom cylinder and other models, shows how gross requirements are netted against 260 on hand and a scheduled receipt of 300, then lot-sized in 250s and offset by a three-week lead time into two planned releases. Planned orders for chrome rod and pistons follow in summary. Capacity requirements planning then loads the rod machining center, revealing an overload in week 3 that is resolved by moving one order earlier and using an alternate lathe.

OPS 405 Week 4 grading rubric: where the points go

Strong MRP papers show every step and keep the numbers consistent. Graders look for a correct bill of materials, an MRP record with gross requirements, scheduled receipts, projected on hand, net requirements, planned order receipts and releases calculated period by period, and correct lead-time offsetting and lot sizing. Credit goes to a capacity requirements plan that converts planned and released orders into hours at a work center, identifies overloads and evaluates realistic ways to resolve them. Explaining how data accuracy and parameter choices affect results shows understanding. Clear tables or step lists and properly formatted APA citations complete the paper.

OPS 405 Week 4 help: mistakes to avoid

The most common error in MRP calculations is forgetting scheduled receipts or counting them twice. List them separately before netting. Another frequent mistake is placing planned order receipts and releases in the same period; releases are offset earlier by the lead time. Students also ignore lot sizes, ordering exactly the net requirement when the supplier ships in fixed quantities. State your lot-sizing rule. Capacity sections often stop at showing an overload; say what the planner will do and what it costs. Finally, remind the reader that MRP is only as good as its data: wrong inventory or lead times make every output wrong. A tutor can walk through your MRP record line by line if it will not balance.

Related OPS 405 sample papers

Other OPS 405 week samples

More BS in Business sample papers

OPS 405 Week 4 questions, answered

What does OPS 405 Week 4 usually cover?

It usually covers material requirements planning and capacity requirements planning: bills of materials, time-phased MRP records, lot sizing, lead-time offsetting and loading work centers to check capacity.

Where can I find a free OPS 405 Week 4 sample paper?

The Week 4 paper above works an MRP record and a capacity plan for a hydraulic cylinder plant; it is free to read with margin notes.

What are gross and net requirements in MRP?

Gross requirements are the total quantity of a component needed in a period. Net requirements are what remains after subtracting projected on-hand inventory and scheduled receipts.

What is lead-time offsetting?

Placing a planned order release earlier than its planned receipt by the item's lead time, so the item arrives when needed.

What is capacity requirements planning?

A detailed check that converts planned and open orders into hours of work at each work center by period, comparing load with available capacity.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official University of Phoenix document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.